Owners of Gotham (224 Lyon) received notification from Lamb Development this morning of another delay in firm occupancy. Owners on the lower floors were expecting the occupancy as of March 24th, but notified today that it is pushed back till April 1st (some higher floors are reporting similar delays).
As is in the notice "Due to some unexpected and additional items identified as required for occupancy by various City Inspectors on Thursday of this week (that will take 5-10 days for the site to complete,) we are giving you a revised firm occupancy date of 1 April 2015."
Lamb Development faced two large and unfortunate set backs during construction by outside trades that have held up completion of the building. They stand by the product, with Brad Lamb saying that "Gotham will be Ottawa's finest residence."
Questions about Gotham condos in Ottawa?